Public Procurement ActCommission proposal · COM(2026) 590 final · 2026/0265 (COD)
EN

Article 74Origin

1.The origin of economic operators or subcontractors shall be determined in accordance with Article 3(1) of Regulation (EU) 2022/1031.

2.The origin of goods shall be determined in accordance with Title II, Chapter 2, Section 1 of Regulation (EU) No 952/2013.

3.The origin of services shall be determined on the basis of the origin of the economic operator or subcontractor providing the service.

4.The overall origin of works shall be determined pursuant to the origin of the economic operator, or subcontractor, providing it. For the European preference requirements, buyers may determine separately the origin of the goods used as part of the works pursuant to paragraph 2.

Read it in the full text →All articles in Part III →